Código I14002 |
Ud m³ |
Resumen Hormigón HNE-15/spb/40-20, árido machacado, "in situ", D<=20 km |
CanPres 0,2500 |
Pres 147,8800 |
ImpPres 36,97 |
|||
---|---|---|---|---|---|---|---|---|
1 | O01009 | h | Peón | 3,0000 | 24,4800 | 73,44 | ||
2 | P01006 | t | Cemento CEM II/A-V 42,5 R a granel (p.o.) | 0,2450 | 128,9500 | 31,59 | ||
3 | P02001 | m³ | Arena (p.o.) | 0,4120 | 26,2500 | 10,82 | ||
4 | P02009 | m³ | Grava (p.o.) | 0,8300 | 22,8200 | 18,94 | ||
5 | P01001 | m³ | Agua (p.o.) | 0,1800 | 0,4800 | 0,09 | ||
6 | M02015 | h | Hormigonera fija 250 l | 0,5000 | 26,0000 | 13,00 |
Texto |